Lesson 3 – Diamond Drilling Procedure

1. EXAMINE GAS MEASURING INSTRUMENT

1.1 Check the number to ensure the allocated instrument is taken.
1.2 Examine the instrument visually for any obvious damages.
1.3 Check the battery to see if it is adequately charged.
1.4 Check the calibration at the testing point. The reading must correspond with the flammable gas mixture as displayed at the testing point.
1.5 When satisfied that the gas measuring instrument is in order the operator must sign for the instrument
1.6 A continuous measuring device should be used if available.

 

2. TEST FOR FLAMMABLE GAS

 

2.1 At the beginning of the shift:
2.1.1 When arriving at the diamond drill cubby, test for flammable gas in the through ventilation.
2.1.2 Test at all cavities in the hanging wall of the cubby.
2.1.3 Test the general atmosphere, covering the entire cubby.
2.1.4 Test the area within 0,5metre radius around the hole.
2.1.5 Test at the collar of the hole or in the case where the rods were not extracted, test at the core stopper. (Above and back end of drill string)

2.2 Tests during Drilling Operations
2.2.1 When water is intersected.
2.2.2 When suspected that flammable gas was intersected (Air bubbles are observed in drilling water in return flow).
2.2.3 When a loss of drilling water is experienced.
2.2.4 When pulling rods, examine after every tenth rod, except when a continuous gas measuring instrument is in place.
2.2.5 Test at core stopper behind the machine for gas prior to inserting an additional rod.
2.2.6 At hourly intervals.
2.2.7 Direct flow drilling.
2.2.8 Reverse flow drilling.

 

3. REVERSE FLOW:

3.1 When using a continuous gas measuring instrument, the instrument must be placed at the highest possible area where methane is likely to accumulate against the hanging wall, above the core stopper.

 

3.2 Direct flow
3.2.1 Test at the collar of the hole, drilling cock or casing pipe every time a rod is being inserted or removed.

3.3 Flammable gas is detected, and evacuation procedures.
3.3.1 Maintain ventilation in a normal manner in accordance with the mine‟s standard instructions.
3.3.2 Open compressed air onto the hole to dilute the flammable gas (the air hose should not be equipped with a tailpiece at the discharge point).
3.3.3 Withdraw all persons to a point of through ventilation, free from any flammable gas.
3.3.4 Post a guard in through ventilation, free from any flammable gas to prevent inadvertent entry of persons.
3.3.5 Report the presence of flammable gas as soon as possible to a Mining Official and Environment Control Department.
3.3.6 The person reported to must sign the operator‟s notebook as proof of acknowledgement.
3.3.7 Follow up if report has received the attention of Senior Mine officials.
3.3.8 If no Mining official is available, barricade the area and mark the barricade properly with the wording “DANGER- FLAMMABLE GAS – NO ENTRY”.

 

At the end of the shift
Return the flammable gas- measuring instrument to the lamp room.

 

Remarks
When using a continuous gas-measuring instrument, the instrument must be placed at the highest possible area where flammable gas is likely to accumulate above the point where drilling water is discharged.

 

3.4 Equipment Used For Diamond Drilling

3.4.1 Saddle clamp
3.4.2 Safety bar plus 18mm x 150mm bolts and nuts for strike block.
3.4.3 Jigger clamp. (75mm)
3.4.4 A-frame plus old „E‟ rods. (Bokkie bar)
3.4.5 Strike block.
3.4.6 Casing clamp with six bolts and nuts (150mm x 18mm), with square washers.
3.4.7 Lubricator with sand trap, air filter and air valves on both ends and spuds.
3.4.8 Loafer hose. (25mm x 3m)
3.4.9 Stuffing box with 25mm high pressure valve and spud.
3.4.10 Water hose.
3.4.11 Air hose.
3.4.12 Water swivel.
3.4.13 High pressure drilling cock. (50mm)
3.4.14 High pressure nipple. (50mm)
3.4.15 Diamond drill couplings and rods.
3.4.16 Rod pusher.
3.4.17 Rod pusher jaw.
3.4.18 Lowering iron, gripper box or safety chuck.
3.4.19 Two swivel pins.
3.4.20 One swivel bolt with washer and nut.
3.4.21 One diamond drill high pressure casing.
3.4.22 Two 24mm x 1.5m wedge bolts with nuts and wedges.
3.4.23 Two wedge bolt extension couplings and rods.
3.4.24 One chuck spanner.
3.4.25 Flat spanners. (17mm)
3.4.26 Two Stillson wrenches.
3.4.27 One marlin spike.
3.4.28 One Hammer (1 kg.)
3.4.29 One cline ruler.
3.4.30 One 30-metre measuring tape.
3.4.31 One 300mm shifting spanner.

 

4. PREPARATION AND DRILLING OF A HORIZONTAL CASING HOLE IN A CUBBY

4.1 Preparation of a drill site by Miner
4.1.1 Before a newly blasted cubby is entered, it must be examined and made safe by a competent person who is the holder of a valid blasting certificate.

 

4.2 Marking off a hole
4.2.1 Ensure that the location of the cubby is correct. (see the survey note )
4.2.2 Locate the peg on the hanging wall and make sure that the peg number corresponds with the number on the survey note.
4.2.3 To put the survey line on the foot – wall, take a charging stick and cut a groove into it on the one end.
4.2.4 Take a nylon cord and tie a nut onto the one end.
4.2.5 Pull the cord through the groove of the charging stick and push the end with the groove up against the survey line.
4.2.6 Pull the other end of the nylon cord so that the nut is just hanging above the foot -wall.
4.2.7 Make a paint mark directly under the nut on the foot -wall.
4.2.8 Go through the same procedure and make another paint mark on the foot – wall further along the line ± 2 metres past the cubby face.
4.2.9 Pull a nylon cord so that it cuts through the middle of both marks on the foot – wall and paint over the cord.
4.2.10 The survey line is now on the foot – wall.
4.2.11 Measure the correct meters from the peg to the cubby face but make sure it corresponds with the distance on the survey note.
4.2.12 If it does not correspond with the plan then make a note stating the correct distance on the plan.
4.2.13 Measure horizontally 1,2m from the side wall of the tunnel into the cubby face, and 1.0m from the foot wall up and make a paint mark. (collar point of hole)
4.2.14 Hold the one end of the nylon cord on the (collaring point) and pull the other end of the nylon cord so that it cuts the survey line.
4.2.15 Move the cline rule set at the degrees required, forward or backwards on the survey line until the correct angel is achieved.
4.2.16 Extend the cord from the collaring point in line with the leg of the cline rule to the opposite side wall, and make a paint mark.
4.2.17 This line will be the direction fore the hole to be drilled on at the correct dip.

 

4.3 Marking off wedge bolt holes
4.3.1 The angle or dip of the hole is marked on the survey note.
4.3.2 All holes must be marked in such a way as to allow enough space behind the machine to pull a 1,5 m rod.
4.3.3 The position of the top wedge bolt is 150 mm above the casing pipe and the bottom wedge bolt 300 mm below the casing pipe on line.

 

4.4 Drilling of wedge bolt and rod stack holes
4.4.1 Blow out air hose.
4.4.2 Connect to the incoming side of the lubricator, secure with a safety chain or sling.
4.4.3 Connect loafer hose to lubricator and machine. (jackhammer)
4.4.4 Drill wedge bolt holes ±1.150 m deep.
4.4.5 Drill two short holes into the side – wall of the cubby to accommodate two old rods. This must be used as a rod stack. Pack all the rods onto the rack with couplings pointed in one direction.

 

4.5 Installing wedge bolts
4.5.1 Blow out the wedge bolt holes with compressed air and water to remove all grit in holes.
4.5.2 Grout the two wedge bolts in and allow it to protrude for ±350 mm.

 

4.6 Rigging-up a machine
4.6.1 The saddle plate assembly is secured to the safety bar by means of two 18mm bolts and nuts.
4.6.2 The casing clamp must be secured to the wedge bolts with four square washers and nuts.
4.6.3 Push the strike block over the safety bar.
4.6.4 Lift the safety bar so that the A-frame and jigger clamp can be moved into position.
4.6.5 Secure the jigger clamp to the A-frame.
4.6.6 Secure the jigger clamp to the saddle clamp by means of a toe bolt.
4.6.7 The frame must be set firmly on a sleeper.
4.6.8 Push the safety bar into the position provided for it between the two sides of the casing clamp and secure by means of a bolt and nut.
4.6.9 Place the machine on the saddle plate and secure by means of two swivel pins and one swivel bolt.
4.6.10 Connect the loafer hose to the outgoing side of the lubricator and onto the spud of the machine and secure with safety chains.
4.6.11 To start drilling the hole, the correct size core barrel, shell and crown must be used.
4.6.12 Push the core barrel fitted with the shell and crown through the opening in the casing- clamp up against the rock face of the hole.
4.6.13 Push a diamond drill rod through the feed screw with the chuck jaws open, and couple to the core barrel.
4.6.14 Connect the water swivel to the rod by means of a coupling. Connect the water hose to the other end of the water swivel.
4.6.15 Clamp the diamond drill rod between the chuck jaws by tightening the dog screws.

 

4.7 Rigging-up a U3 9B and LM90 hydraulic machine with a fan frame
4.7.1 Clean footwall to solid footwall
4.7.2 Though cement pad 100mm thick
4.7.3 Position the machine frame
4.7.4 Drill pin holes.
4.7.5 Pin machine tighten all pin down bolts.
4.7.6 Lift machine in position on the frame.
4.7.7 Tighten the machine on frame.
4.7.8 Lift machine into position with hydraulic cylinder.
4.7.9 Install stabilizers in place tighten stabilizers
4.7.10 Place power pack in position. Power pack to be placed on a level surface.
4.7.11 Connect hydraulic hoses between power pack and machine and control. (Ensure hoses are connected properly)
4.7.12 Check oil level and top up
4.7.13 Connect power supply to power pack (Electrician to connect power supply)
4.7.14 Make sure machine gear in neutral.
4.7.15 Check correct rotation of electric motor.
4.7.16 Connect water hose to oil cooler
4.7.17 Check forward and back movement of machine
4.7.18 Commission machine (qualified person)

4.8 Drilling a casing hole
4.8.1 Make a small recess in rock face at collar position.
4.8.2 Open water.
4.8.3 When water comes through the bit, start rotating the machine very slow. The bit must be right up against the face and the machine in first gear.
4.8.4 Ensure that the core barrel is not whipping.
4.8.5 Ensure that the bit spins in one position.
4.8.6 Ensure the cutting edge of the bit has penetrated into the rock
4.8.7 Check if machine is still on line.
4.8.8 Speed up the revs of the machine.
4.8.9 Drill casing to the required depth.
4.8.10 Close water.
4.8.11 Loosen the nuts of on the wedge bolts and remove the square washers.
4.8.12 Move the rig backwards and swing the casing clamp to the side so that casing pipe can be installed.
4.9 Installing a casing pipe.

 

The following checks to be done prior to installation of a casing pipe:
4.9.1 Check for straightness.
4.9.2 Check for dents.
4.9.3 Check threads.
4.9.5 Check if casing is clear of any foreign objects.
4.9.6 Check if casing is clean and clear of grease or paint.
4.9.7 Check if casing is the required length.
4.9.8 Check if reaming shell fits through the casing.
4.10 The following steps to be followed when installing a casing pipe:
4.10.1 Test for flammable gas.
4.10.2 Remove all grit and water by using compressed air or water.
4.10.3 See that drilling cock is functioning correctly.
4.10.4 Screw the drilling cock tightly onto the casing pipe.
4.10.5 Fill the casing hole with a mixture of cement and calcium chloride.
4.10.6 Drive the casing into the hole with a wooden sleeper or block, leave enough space between the face and the drilling cock to rethread the casing pipe if the threads get damaged.
4.10.7 Allow cement to set for ± 4 hours.

 

5. PREPARATION AND DRILLING OF A VERTICAL HOLE

5.1 Preparation of drill site by Miner
5.1.1 Before a newly blasted drill site is entered, it must be examined and made safe by a competent person who is the holder of a valid blasting certificate.

5.2 Drilling and cementing of wedge bolts
5.2.1 Install temporary support as per mine standard (See SOP 01) using two cam locks or acrow props with a spacing of 1,75 M apart from each other.
5.2.2 Drill the wedge bolt holes with a pneumatic drill (jackhammer) which is usually obtained from the miner of that section, or drill the holes with diamond drill (E size)
5.2.3 Use the air and water hoses of the diamond drill for drilling.5.2.4 After having blown air through the air hose, fill the lubricator with oil and connect the hose. (Secure hose with a safety chain or safety sling).

5.2.5 Connect the pneumatic drill air hose onto the rod pusher hose connection and start drilling the holes where required. Drill the top – hole +5º from line of hole and bottom hole -5º of line of hole, deep enough to allow the wedge bolts to protrude +0,35m.
5.2.6 Blow the wedge bolt holes clear of all grit and fill with cement.
5.2.7 Fit a steel wedge in the split end of the wedge bolt, fit nut flush with wedge bolt head and drive into the hole with a sleeper.

 

5.3 Rigging of the Diamond drill machine with a upright bar
5.3.1 Fit the casing clamp over the wedge bolts and secure as per sketch.
5.3.2 Fit the safety bar in the correct position onto the safety clamp and allow it to hang straight down.
5.3.3 Rig the upright bar correctly on a sleeper and in the correct position. Fit the cross bar by means of the cross clamp in line with the saddle clamp. Secure the safety bar by means of the jigger clamp, without moving the safety bar off line. Tighten all bolts and nuts properly.
5.3.4 Fit the machine on the rig and line up.
(Rigging with a “A” frame refer to point F at Horizontal hole)

5.4 Drilling of a casing hole
5.4.1 Make a small recess in the rock face where the hole is to be collard.
5.4.2 Screw the casing core barrel fitted with a shell and crown onto the rod in the machine. Push the rod with the crown firmly against the rock in the recess and fasten the chuck jaws.
5.4.3 Screw the water swivel onto the other end of the rod, and apply the water.
5.4.4 When the water comes through the bit, start rotating the machine very slowly. Ensure the rod does not whip and the bit spins in one position.
5.4.5 When the cutting edge of the bit has penetrated well into the rock, stop and check if the machine is still drilling on line and at the required dip.
5.4.6 Drill to required depth, rig off the machine and remove the casing clamp.
5.4.7 Wash the hole, clear of all grit.

5.5 Installation of the casing pipe.
5.5.1 Clean the casing pipe. Plug the threaded end with a piece of paper.
5.5.2 Make a mixture of sloppy cement and fill the casing pipe. Push the pipe up the hole.
5.5.3 Take a damaged rod (or charging stick) and push it into the bottom end of the casing pipe against the paper plug.
5.5.4 Whilst pulling the casing pipe downwards, push the rod or charging stick up into the casing pipe against the paper plug, forcing the cement into the hole.
5.5.5 When all the cement is out of the casing pipe, remove the rod and drive the pipe back up the hole with a sleeper.
5.5.6 Secure with two steel wedges and allow the cement to set.

5.6 Inserting or extracting rods in and out of a hole.
5.6.1 Use a lowering iron to hold the rods when moving rods in or out of a hole.
5.6.2 Place the lowering iron above the strike block.
5.6.3 Use the rod pusher when pushing a long string of rods up a hole.
5.6.4 Keep the rod pusher jaw properly adjusted as to prevent it from slipping. Keep clear from the immediate vicinity of the drill string.

 

6. RE-DRILLING OF A CASING
6.1.1 Before drilling is commenced, ensure that the clamps, bolts and wedge bolt nuts are tight.
6.1.2 Fit the correct size shell and crown onto the rod protruding through the machine chuck and push it up against the cement in the hole.
6.1.3 Fasten the chuck jaws, screw the water swivel onto the other end of the rod, open the water and commence drilling.
6.1.4 Drill until the crown has penetrates the rock face, stop and remove the water swivel, switch to reverse flow and proceed with drilling.

6.2 Continues core drilling
6.2.1 Check for flammable gas.
6.2.2 Fit a stuffing box onto the 50mm high- pressure nipple with a 25mm HP valve and spud to accommodate the water hose.
6.2.3 Push the crown shell and rod in to the casing pipe.
6.2.4 Connect the 1,5m rod in the machine to the rod in the hole.
6.2.5 Push the crown against the rock face in the hole.
6.2.6 Push the two steel rings and three rubber gaskets over the rod into the stuffing box.
6.2.7 Push the wing nut over the rod and secure to the stuffing box.
6.2.8 The gear selector handle is moved to the 1st gear position.
6.2.10 Clamp the rod in the chuck by tightening the dog screws evenly.
6.2.11 Apply a thin layer of grease onto the rods.
6.2.12 Couple the water hose to the high- pressure valve on the stuffing box and fit the core stopper to the rod protruding behind the machine (reverse flow).
6.2.13 Rotate the drill string slowly until the water change colour.
6.2.14 Slack the wing nut on the stuffing box to allow a little seepage of water between the rods and rubber gaskets to prevent the gaskets from burning.
6.2.15 The revs of the machine can now be increased.
6.2.16 Never change the gears on the machine whilst the drill string is under pressure.
6.2.17 Keep clear of rotating parts whilst drilling.
6.2.18 No persons to be allowed to stand behind the machine during drilling operations.
6.2.19 Drill until the back end of the feed screw is approximately 100mm outside the feed nut at the back of the machine.
6.2.20 Close the water supply and re-chuck.

6.2.21 Loosen the core stopper with a wrench, unscrew the core stopper from the rod threads holding the core stopper firmly by hand with the perforated tail piece in the rod end.
6.2.22 Open the water supply slowly as to push the core out of the rod, but controlling the core with the core stopper.
6.2.23 Slowly remove the core stopper and remove the core by hand.
6.2.24 When all the core available is removed close the water supply and replace the core stopper.

 

6.3 Re-chucking on a horizontal hole (no pressure on drill string)
6.3.1 Mark one dog screw.
6.3.2 Loosen the chuck by loosening the marked dog screw.
6.3.3 Move the gear selector handle to the neutral position.
6.3.4 Reverse the machine until the chuck is back at the starting position.
6.3.5 Tightened the marked dog screw, open the water and continue drilling.

6.4 Re-chucking LM 90 machine
6.4.1 All people to stand clear from machine while re-chucking.
6.4.2 Hydraulic operation on gripper and chuck.

6.5 Re-chucking with a safety chuck (drill string under pressure)
6.5.1 Where extreme volumes and pressures of water bearing fishers are evident, an additional safety chuck must be used. This chuck is fitted between the stuffing box and the strike block as an extra safety precaution.
6.5.2 When the intersection of water or flammable gas is evident stop the machine immediately.
6.5.3 Ensure that there are no people behind the machine.
6.5.4 Move the safety chuck in a position against the strike block and tighten the dog screws.
6.5.5 Test for flammable gas, if gas is detected. (Rev. to procedure to test for

6.6 Removing rods using the safety chuck
6.6.1 Ensure the safety chuck is properly secured and is against the strike block.
6.6.2 Ensure that there are no people behind the machine.
6.6.3 Slack the chuck on the machine.
6.6.4 Change to 4Th gear.
6.6.5 Advance the machine chuck to the maximum feed available.
6.6.6 Change gear lever to neutral position.
6.6.7 Secure the machine chuck.
6.6.8 Ensure that there are no people behind the machine.
6.6.9 Slack the safety chuck.
6.6.10 Reverse the machine to starting position.
6.6.11 Secure the safety chuck against the strike block.
6.6.12 If possible, remove a rod from drill string.
6.6.13 Follow the above procedures until all rods have been removed.

6.7 Rod puller operations U39B air machine
6.7.1 The use of a rod puller is to extract or insert rods in a drill hole.
6.7.2 Employ the correct rod puller for the specified work
6.7.3 A rod puller jaw or pulling dog cam is secured to the rod puller arm to grip the rods
6.7.4 Chains and wrenches must not be used to grip the rods.
6.7.5 Whilst handling rods with a rod puller, safety devices such as stop blocks lowering arms and foot clamps must be used to hold the rods.
6.7.6 Workers to stand clear whilst pushing or pulling rods.
6.7.7 The correct alignment of the rod puller is of vital importance. Incorrect alignment can cause accidents, as the rods can break at the joints.
6.7.8 Ensure that all the rod puller bolts and the securing bolts are tight.
6.7.9 Keep hands clear from the rod puller piston whilst it is in operation.
6.7.10 Visually check that all the rod pulling mechanisms are in place and secured whilst in operation.
6.7.11 Rod gripping devices that are worn or damaged must be replaced.
6.7.12 Never assist the rod gripping devices with wrenches or chains, this practice could cause serious accidents.
6.7.13 Disconnect the air or hydropower from the rod puller when it is not in operation and remove it from the saddle clamp.

 

6.8 Rod puller operations U39B hydraulic machine
6.8.1 The use of a rod puller is to extract or insert rods in a drill hole.
6.8.2 Employ the correct rod puller for the specified work
6.8.3 Chains and wrenches must not be used to grip the rods.
6.8.4 Ensure hydraulic hoses are properly connected between rod puller and control.
6.8.5 Whilst handling rods with a rod puller, safety devices such as a rod pulling mechanism must be use.
6.8.6 Workers to stand clear whilst pushing or pulling rods.
6.8.7 The correct setting of the rod puller is of vital importance. Incorrect alignment can cause accidents, as the rods can break at the joints.
6.8.8 Ensure that all the rod puller bolts and the securing bolts are tight.
6.8.9 Stand clear from the machine whilst pulling rods.
6.8.10 Visually check that all the rod pulling mechanisms are in place and secured whilst in operation.
6.8.11 Rod gripping jaws that are worn or damaged must be replaced.
6.8.12 Never assist the rod gripping devices with wrenches or chains, this practice could cause serious accidents.
6.8.13 Pulling mechanisms are in place and secured whilst in operation.
6.8.14 Rod gripping devices that are worn or damaged must be replaced.
6.8.15 Never assist the rod gripping devices with wrenches or chains, this practice could cause serious accidents.

6.9 Rod puller operations LM 90 hydraulic machine
6.9.1 Stand clear from machine whilst extracting or inserting rods. .
6.9.2 Ensure hydraulic hoses are properly connected between machine and control.
6.9.3 LM 90 use hydraulic chuck and rod holder to extract or insert rods.
6.9.4 Chuck and rod holder jaws that are worn or damaged must be replaced.
6.9.5 Never assist the machine whilst pulling rods with wrenches or chains, this practice could cause serious accidents.

6.10 Daily rod care.
6.10.1 Check for straightness.
6.10.2 Check for dents.
6.10.3 Check wall thickness.
6.10.4 Check threads.
6.10.5 Check if rods are clear from any foreign objects.

 

6.11 Packing of core
6.11.1 Pack core correctly in clean core boxes.
6.11.2 Clean the core, tape and mark as prescribed by the geologist.
6.11.3 See that core boxes are secured and brought to surface.

 

7. RIGGING DOWN AND TRANSPORTING OF EQUIPMENT

7.1 Rigging down a machine from a vertical hole
7.1.1 The last two rods to be left in the machine.
7.1.2 Disconnect energy source and water feed.
7.1.3 The one end of the two rods must rest on a plank on the foot wall.
7.1.4 Secure the rods with the machine chuck.
7.1.5 Move a flat material car into position to lower the machine onto.
7.1.6 Remove the swivel pin from the saddle plate.
7.1.7 With the machine resting on the two rods, tilt the machine sideways and lower slowly directly onto the flat material car.
7.1.8 Remove the casing clamp and the safety bar.
7.1.9 Remove the jigger clamp.
7.1.10 Remove the cross bar.
7.1.11 Remove the cross clamp from the upright bar.
7.1.12 Examine the hanging wall above the upright bar, and make safe necessary.
7.1.13 Attach a guide chain to the upright bar to guide it into a safe tilting direction
7.1.14 Loosen double foot bar jack whilst assistants pull the upright in to the desired direction. The hanging should be observed at all times while the foot bar jacks are loosened.
7.1.15 Tilt and lower the upright bar down to the foot wall
7.1.16 Remove the two cam lock props using the remote releasing devices.

 

7.2 Rigging down LM 90 and U39B hydraulic machine
7.2.1 Remove rods from machine.
7.2.2 People to stand clear from machine.
7.2.3 Lower machine to machine bed with hydraulic cylinder.
7.2.4 Disconnect power on power pack. (Electrician).
7.2.5 Disconnect all hydraulic hoses from machine power pack and control.
7.2.4 Lift machine from fan frame with chain block.
7.2.5 Loosen pin bolts on machine frame.

7.3 Loading and transporting equipment
7.3.1 Load the rods next to the machine onto the flat material car.
7.3.2 Remove one of the two rods from the machine.
7.3.3 Load the rest of the equipment onto the material car and secure properly.
7.3.4 Write down the destination of where the equipment must go onto the material car.
7.3.5 Arrange for transporting of equipment with the Mine Official in charge.
7.3.6 Clean the drill site before leaving the area.
7.3.7 Plug off hole if required so by Geologist.

8. DIAMOND DRILLING

8.1 U39B Electro Hydraulic Power Pack
8.1.1 The use of a Power Pack is to drive an Electro Hydraulic machine
8.1.2 Ensure power pack is placed level in the correct position.
8.1.3 Check correct power supply.
8.1.4 Lock out devices in place
8.1.5 Connect power supply and correct rotation. (Electrician)
8.1.6 Check oil level.
8.1.7 Check oil cooler.
8.1.8 Ensure hydraulic hose connection are done properly and no oil leaks
8.1.9 Fire extinguisher in place.

8.2 Flame Proof Electro Hydraulic Power Pack
8.2.1 Ensure power pack is placed level in the correct position.
8.2.2 Check correct power supply.
8.2.3 Electric starter box sealed and lock out device in place.
8.2.4 Connect power supply and correct rotation. (Electrician)
8.2.6 Check oil level.
8.2.7 Check oil cooler.
8.2.8 Ensure hydraulic hose connection are done properly and no oil leaks
8.2.9 Fire extinguisher in place.

Skip to toolbar